Concrete work continues after Tarbela T-5 rock collapse

“Concrete work and dewatering are continuing after a weak rock mass collapsed at the Tarbela T-5 hydropower project site.”
Key points
- Concrete work and dewatering are continuing after a weak rock mass collapsed at the Tarbela T-5 hydropower project site.
- Officials say critical project structures were not damaged, while the incident’s cause and any losses remain under assessment.
Civil work is under way to seal the crater created after a weak rock mass collapsed at the Tarbela Dam Fifth Extension Hydropower Project, according to officials and people involved at the site in Haripur.
The collapse occurred on Monday during excavation work at the project’s second-bench connecting tunnel. An official handout said water from the intake pit entered the tunnel and the powerhouse area, while workers carrying out routine duties were evacuated safely.
Officials and the Haripur district administration said the water had been drained from the intake pit and was no longer entering downstream work areas. Dewatering work at the under-construction powerhouse was also continuing, they said.
Project-side sources said concrete was being poured to close the opening, with engineers, contractors and workers focusing on the affected area. They estimated that the civil work and dewatering could be completed within about a week, though that remains subject to site conditions and the final technical assessment.
The sources said the collapse had not damaged the main tunnel, powerhouse structure, tailrace culvert or switchyard. They also said reports were being prepared every six hours for stakeholders, while an initial incident report had been submitted to the Water and Power Development Authority chairman and the Ministry of Water Resources.
The cause of the rock collapse and the scale of any loss are still being assessed. A final report is expected to be submitted to the Prime Minister’s Office, the water ministry and other stakeholders in the coming days. Most of the project’s roughly 3,000 workers have reportedly been told to remain off site until further notice, with only essential operators continuing work.
Corrections & clarifications
Spot an inaccuracy or need more detail? Email connect@newsnexus24.com. Publication time is shown above.





