World Bank lowers Punjab education project implementation rating

“The World Bank has lowered the implementation rating of Punjab’s $150 million education project because technical assistance and baseline data remain pending.”
Key points
- The World Bank has lowered the implementation rating of Punjab’s $150 million education project because technical assistance and baseline data remain pending.
- The project has nevertheless reported enrolment gains and expanded early-childhood education standards in more than 1,000 schools.
The World Bank has lowered the implementation-progress rating of a $150 million education project in Punjab, citing delays in technical assistance and the absence of baseline data. The project is intended to improve access to quality education and learning outcomes for children across the province.
The lender revised the project’s overall implementation rating from satisfactory to moderately satisfactory. Its rating for progress towards the project’s development objectives remained moderately satisfactory, while the overall risk assessment was unchanged at moderate.
Despite the downgrade, the World Bank said the project had continued to make progress against key targets, including financial targets for the previous fiscal year. It said progress had also been recorded across the project’s performance-based conditions.
Enrolment in public-private partnership schools has risen substantially from the project baseline, with the fourth-year target achieved ahead of schedule. The project has also helped 1,092 additional schools meet quality standards for early childhood care and education.
However, classroom construction has not yet begun, although preparatory work has progressed. The World Bank said formal restructuring was needed to reflect the Punjab government’s revised construction plan.
The lender also said technical assistance needed to support several reform deliverables had not been mobilised. Baseline data remains unavailable and is expected to be addressed through the planned restructuring process.
The World Bank said continued progress on these arrangements, along with the start of classroom construction, would be necessary to maintain implementation momentum and achieve the project’s intended results.
The loan was approved in June 2024 and is scheduled to close in June 2029. The project, known as GRADES, aims to increase participation in pre-primary and primary grades and improve reading proficiency among primary-school children in Punjab.
The programme is designed to improve learning outcomes, help address learning losses linked to the Covid-19 pandemic, strengthen school management and expand school participation. It is expected to directly benefit around five million children, 7,000 headteachers, 165,000 teachers and more than 3,000 teacher mentors.
Project documents show that more than seven million children in Punjab were out of school as of June 2024. The programme seeks to reduce that number while improving foundational learning and the quality of teaching, learning materials and school environments.