Naltar Phase-III power project starts operations in Gilgit

“The 16-megawatt Naltar Phase-III hydropower project has become operational in Gilgit after more than a decade of delays.”
Key points
- The 16-megawatt Naltar Phase-III hydropower project has become operational in Gilgit after more than a decade of delays.
- The Gilgit-Baltistan chief minister said it would add eight to nine hours of electricity for residents and reduce loadshedding.
The 16-megawatt Naltar Phase-III hydropower project has started operations in Gilgit, more than a decade after it was launched. Gilgit-Baltistan Chief Minister Amjad Hussain said the project would provide residents with an additional eight to nine hours of electricity and help reduce loadshedding.
The chief minister visited the facility, where officials from the water and power department briefed him on electricity supply arrangements for Gilgit city. He said the project had become operational on Sunday.
Naltar Phase-III and the 14-megawatt Naltar Phase-II project were included in the Public Sector Development Programme in 2009 and launched in 2012. The chief minister said both projects went through three revisions during their extended development period.
According to the chief minister, Phase-III had reached only 3 per cent progress by 2015. Work remained at 23 per cent through 2024 before accelerating to 72 per cent in 2025 and reaching completion this year.
Amjad Hussain said he had asked Prime Minister Shehbaz Sharif to formally inaugurate the project. He also said the new capacity would provide immediate relief to residents facing continued electricity shortages.
The chief minister said a lasting solution required progress on other regional hydropower schemes. He said the 40-megawatt Hanzel project had been stalled for seven years and that its tendering process would be restarted within the next three months.
He added that issues concerning the 54-megawatt Attabad project had been resolved. He said efforts were also under way to complete the Harpo and Shagarthang hydropower projects as part of wider plans to improve electricity availability in Gilgit-Baltistan.