Rock collapse halts work at Tarbela’s fifth extension project

Rock collapse halts work at Tarbela’s fifth extension project
“A rock collapse during excavation at the Tarbela fifth extension project caused water to enter work areas, forcing a suspension of construction and the evacuation of workers.”
— Editorial Team

Key points

  • A rock collapse during excavation at the Tarbela fifth extension project caused water to enter work areas, forcing a suspension of construction and the evacuation of workers.
  • Authorities said no casualties were reported, the main tunnel remained intact and dewatering work was under way.
General|By Editorial Team|Published

Construction work at the Tarbela Dam Fifth Extension Project was suspended after a rock mass collapsed during excavation and allowed water to enter nearby work areas, authorities said. An emergency was declared at the site and workers were moved to safer locations.

The incident occurred during excavation of the second Bench Connecting Tunnel. Water from the intake pit entered a tunnel and the under-construction powerhouse area after the weak rock section gave way, according to the Water and Power Development Authority.

All workers were evacuated safely and no injuries or deaths were reported. The authority said the intake pit had been drained and that no further water was flowing into downstream work areas. Dewatering operations at the under-construction powerhouse had also begun.

Officials said the main tunnel, the under-construction powerhouse, the tailrace culvert and the switchyard had not been damaged. Senior officials, the project engineer and the contractor were assessing the site to determine whether any other structures in the working area were affected.

District authorities said there was no immediate threat of flooding or inundation downstream. However, additional releases from Tarbela Dam were expected to raise the flow and level of the Indus River, prompting public-safety advice for communities near the riverbanks.

Residents were urged to avoid bathing, swimming and boating in the Indus River and to follow official safety notices. The district administration also asked the public not to rely on unverified reports about the incident.

The project is designed to add 1,530 megawatts of generating capacity through the conversion of Tunnel No. 5. Once completed, the extension is expected to increase Tarbela’s installed capacity from 4,888MW to 6,418MW.

The work has already faced setbacks. A government inquiry into an earlier cofferdam collapse identified unauthorised design changes after the contract award as one contributing factor. That incident was linked to a major cost increase and delays, with the project’s expected completion moved from 2026 to June 2028 before the latest disruption.