World Bank flags delays in Pakistan’s $425m grid project

World Bank flags delays in Pakistan’s $425m grid project
“The World Bank has flagged delays in Pakistan’s $425 million power-transmission modernisation project, with $124.31 million still undisbursed before its December 2026 closing date.”
— Editorial Team

Key points

  • The World Bank has flagged delays in Pakistan’s $425 million power-transmission modernisation project, with $124.31 million still undisbursed before its December 2026 closing date.
  • Slow progress on the Islamabad West Substation and gaps in revised delivery targets remain key concerns.
Business|By Editorial Team|Published

The World Bank has identified major delays in Pakistan’s $425 million National Transmission Modernisation-I Project, with more than $124 million still undisbursed as the programme approaches its December 31, 2026 closing date.

The project was approved in December 2017 to strengthen selected parts of the national transmission network and modernise key business processes. It is being implemented by the National Transmission and Despatch Company, now operating as the National Grid Company.

According to the lender’s latest documents, $255.53 million has been disbursed from the original financing package. The remaining $124.31 million has not been utilised, with slow progress on the Islamabad West Substation contract identified as the main reason for the gap.

The project’s overall implementation progress and progress towards its development objectives remain rated as moderately satisfactory. However, several physical targets have been reduced through revisions, while actual delivery remains below those revised benchmarks.

The original plan included 36 new or upgraded substations, a target later reduced to 24. By November 2025, 17 substations had been completed. The target for transmission-line construction or rehabilitation was cut from 131 kilometres to 11 kilometres, with 7.2 kilometres completed.

The report also recorded a substantial gap in transmission-loss reduction. Savings stood at 24.31 gigawatt-hours against a revised target of 414 GWh. Additional substation capacity reached 3.18 million kVA, compared with a target of 12.516 million kVA.

The project’s enterprise resource planning system was also behind schedule and had not become operational by November 2025, despite an earlier expectation that it would be functioning by April 2026. The programme has undergone three restructurings since October 2023.

The lender retained the project’s overall risk rating at substantial and raised the fiduciary-risk assessment from moderate to substantial. Financial reporting has improved, with the time taken to submit audited statements falling from 14 months to five months, while an integrated budgeting and reporting system has become operational.

The remaining period before the revised deadline will be critical for completing delayed work, especially the Islamabad West Substation contract. The project’s performance matters for Pakistan’s efforts to improve transmission reliability and manage power-sector infrastructure more efficiently.